New Grant PUD line under construction

Print Article

Courtesy photo The construction phase of a project to build a new power line between Rocky Ford and Moses Lake should be finished by the end of the year. The line will go into in fall 2018.

EPHRATA — All the electrical poles currently being installed along SR 17 between Rocky Ford and Moses Lake should in place by the end of 2017. However, the line won’t go into operation for about a year.

Grant PUD commissioners received an update on the project at the regular meeting Tuesday. The Rocky Ford line is one of two major electrical system projects currently underway, said Randy Kono, PUD electrical engineer.

Currently the poles are going up along SR 17. “A lot of big sticks being put in the ground,” Kono said.

“How much does each of those big sticks cost?” asked commissioner Larry Schaapman. Kono said the laminated wood poles are about $10,000 to $15,000 each.

The second project is a transmission line at the Quincy Plains substation. Both are designed to upgrade and expand the existing system, Kono said.

The line between the Rocky Ford and Dover substations is being installed “to meet load growth in the Moses Lake area,” Kono said. Currently five substations serve that area, one providing electricity to the other four. If that one substation breaks down, currently there’s no way to get electricity to the other four, Kono said. The new line will fix that.

Total project cost will be about $8 million, Kono said. The winning bid for the pole-setting part of the project was $2,602,334. About $2.8 million will be spent on materials, he said.

The PUD did have to pay an additional $338,133 for transmission wire to replace some that was damaged. Damaged wire is a problem, Kono said, because “they (damaged wires) cause a phenomenon called corona. Corona is bad,” he said. Corona discharges can damage nearby equipment and release gases that can be harmful to humans.

The contract specifies that the poles should be installed by Dec. 22. The line actually won’t start transmitting electricity until fall 2018. Some work is required at the Rocky Ford substation before the lines can go into service, Kono said.

The Quincy Plains project will provide electricity to substations that serve the large industrial customers along Road 11 Northwest. Total project cost is about $3 million, Kono said. The contract to build the line was $896,445.

“There was a plan to energize the Quincy Plains (line) on Saturday (Oct. 7),” Kono said. However, “there was a wind advisory issued on Saturday,” and the wind was blowing so hard the project was delayed. Utility district officials are talking with the customers who will be served by the line to determine a new service date, he said.

Cheryl Schweizer can be reached via email at education@columbiabasinherald.com.

Print Article

Read More Local News

 3 injured in 2-vehicle collision near Quincy

October 20, 2017 at 5:00 am | Columbia Basin Herald QUINCY — Three people were injured in a two-vehicle collision near Quincy Thursday afternoon. About 12:20 p.m. Lindsey Blackwell, 20, of Cashmere, was turning from eastbound state Route 28 onto Whit...

Comments

Read More

Archaeology Days next week

October 20, 2017 at 5:00 am | Columbia Basin Herald PRIEST RAPIDS DAM — The Grant County PUD will sponsor its annual look at the science and techniques of archaeology Wednesday and Thursday at the Wanapum Heritage Center at Priest Rapids Dam. Youth Da...

Comments

Read More

Moses Lake woman charged for taking vehicle

October 20, 2017 at 5:00 am | Columbia Basin Herald MOSES LAKE — A Moses Lake woman did not give police a reason why she took a vehicle from a Moses Lake neighborhood, took off and later returned to the same neighborhood and left the car behind. Gran...

Comments

Read More

Othello to make school bond decision Monday

October 20, 2017 at 5:00 am | Columbia Basin Herald OTHELLO — The Othello School Board hasn’t reached a decision about which projects it will include in a construction bond to be offered to voters in February. Board members discussed their options at ...

Comments

Read More

Contact Us

(509) 765-4561
PO Box 910
Moses Lake, WA 98837

©2017 Columbia Basin Herald Terms of Use Privacy Policy
X
X